PERANCANGAN LABORATORIUM PADA CAMPURAN ASPHALT CONCRETE-BINDER COURSE (AC-BC) DENGAN MENGGUNAKAN ASPAL PEN 60/70 DAN ZEOLIT ALAM SEBAGAI FILLER
Indonesia has a wealth of natural resources is high, including mineral resources into pavement materials. Utilization of natural resources such as raw materials pavement still has not been developed, especially to overcome the problems related to premature pavement damage. Asphalt Pen. 60/70 and...
Saved in:
Main Authors: | , |
---|---|
格式: | Theses and Dissertations NonPeerReviewed |
出版: |
[Yogyakarta] : Universitas Gadjah Mada
2014
|
主題: | |
在線閱讀: | https://repository.ugm.ac.id/133798/ http://etd.ugm.ac.id/index.php?mod=penelitian_detail&sub=PenelitianDetail&act=view&typ=html&buku_id=74626 |
標簽: |
添加標簽
沒有標簽, 成為第一個標記此記錄!
|
總結: | Indonesia has a wealth of natural resources is high, including mineral
resources into pavement materials. Utilization of natural resources such as raw
materials pavement still has not been developed, especially to overcome the problems
related to premature pavement damage. Asphalt Pen. 60/70 and natural zeolite is a
natural asset that can be used, but the study linked the two materials are still not
widely practiced.
Merging the two materials in the testing done with the design of the test
specimen using 5 filler content variation, the variation of1 (100% stone dust: 0%
natural zeolite), variation 2 (75% stone dust: 25% natural zeolite), variation 3 (50%
stone dust: 50% natural zeolite), variations4 (25% stone dust: 75% natural zeolite)
and variation 5 (0% stone dust: 100% naturalzeolite). Having obtained the optimum
bitumen content of each variation then testing Marshall with soaking time of 0,5
hours and 24 hours, then the Indirect Tensile Strength testing.
The results were obtained for the optimum bitumen content variation 1 is
5,8% |
---|