SISTEM PENGELOLAAN DAN PRODUKTIVITAS ALAT BERAT PROYEK PEMBANGUNAN RITA SUPERMALL DAN SWISS BELHOTEL PURWOKERTO
Construction of tall buildings in desperate need of auxiliary equipment such as heavy equipment. The use of heavy equipment on construction projects have different types according to their functions and aplications. Therefore, a good management system is required. It is intendend that the pattern of...
Saved in:
Main Authors: | , |
---|---|
格式: | Theses and Dissertations NonPeerReviewed |
出版: |
[Yogyakarta] : Universitas Gadjah Mada
2014
|
主題: | |
在線閱讀: | https://repository.ugm.ac.id/131894/ http://etd.ugm.ac.id/index.php?mod=penelitian_detail&sub=PenelitianDetail&act=view&typ=html&buku_id=72404 |
標簽: |
添加標簽
沒有標簽, 成為第一個標記此記錄!
|
總結: | Construction of tall buildings in desperate need of auxiliary equipment such
as heavy equipment. The use of heavy equipment on construction projects have
different types according to their functions and aplications. Therefore, a good
management system is required. It is intendend that the pattern of efficiency of time,
effort, and care techniques in the machine can work well without the wasteful
expense that should not be issued.
System management and productivity of heavy equipment includes the
selection, procurement, placement tool, method execution of work, productivity,
maintenance, and problem related to heavy equipment used in construction Rita
Supermall Purwokerto.
Based on the observation and analysis can be concluded that the
implementation of the machine work that includes excavation and disposal of soil,
steel fabrication, formwork and casting (columns, beams, floor plate and core wall)
use the heavy equipment on each type of work is optimal because the production
capacity already over capacity tool. However, the implementation of the excavating
and disposal of soil needs optimized job to pursue the production delay. |
---|